Dept. of Trans. PROGRESS Serial No. Contract No. 20-266-07-08 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 033 Payment period ending: 09-20-20 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,624,774.67 257,129.69 2. a. Extra Work 1,359,515.18 201,335.05 b. Adustment Comp. -27,183.09 -8,732.65 3. Materials on Hand 4. Earned Subject to Retention 44,957,106.76 449,732.09 5. Mobilization 3,444,601.08 0.00 6. Total Work Completed 48,401,707.84 7. Deductions -50,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,351,707.84 449,732.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 449,732.09