Dept. of Trans. PROGRESS Serial No. Contract No. 21-053-11-36 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 99% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 036 Payment period ending: 02-20-21 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,646,113.20 4,045.22 2. a. Extra Work 1,370,808.63 0.00 b. Adustment Comp. -27,183.09 0.00 3. Materials on Hand 4. Earned Subject to Retention 44,989,738.74 4,045.22 5. Mobilization 3,444,601.08 0.00 6. Total Work Completed 48,434,339.82 7. Deductions -64,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,370,339.82 4,045.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,045.22