Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-347-09-51 08-0J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-215-0.0/2.7 04LN-6208(23) 08-RIV-215-45.1/45.3 Progress payment No. 041 Payment period ending: 06-23-21 MYERS-RADOS A JOINT VENTURE 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,661,687.30 0.00 2. a. Extra Work 1,390,791.65 19,983.02 b. Adustment Comp. -8,315.89 18,867.20 3. Materials on Hand 4. Earned Subject to Retention 45,044,163.06 38,850.22 5. Mobilization 3,444,601.08 0.00 6. Total Work Completed 48,488,764.14 7. Deductions -64,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,424,764.14 38,850.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,850.22