Dept. of Trans. PROGRESS Serial No. Contract No. 08-206-13-54 08-0J6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 84% 08-SBD-138-14.2/23.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-18-08 GRAHAM CONTRACTORS INC P O BOX 26770 SAN JOSE CA 95159 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 268,655.82 155,011.87 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 268,655.82 155,011.87 5. Mobilization 6. Total Work Completed 268,655.82 7. Deductions 8. a.Contract Retentions -13,432.79 -2,068.39 b. Unsatisfactory Prog. -7,750.59 -7,750.59 c. Reduction after 95% Comp. 9. Total pay to Contractor 247,472.44 145,192.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,192.89