Dept. of Trans. FINAL Serial No. Contract No. 09-182-13-47 08-0J6604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-5726 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-10-09 D C HUBBS CONSTRUCTION 37306 VISTA VIEW DRIVE YUCAIPA CA 92399 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 626,660.00 0.00 2.a. Extra Work 35,146.23 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 661,806.23 0.00 5. Mobilization 6. Total Work Completed 661,806.23 7. Deductions 8. a.Contract Retentions -31,647.56 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,647.56 0.00 9. Total pay to Contractor 661,806.23 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00