Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-313-07-44 08-0J9204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-16.0/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-19-10 VICTORY ENGINEERS INC 575 E ALLUVIAL AVENUE STE 106 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 231,432.50 0.00 2.a. Extra Work 9,375.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 240,807.50 0.00 5. Mobilization 6. Total Work Completed 240,807.50 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 240,807.50 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00