Dept. of Trans. PROGRESS Serial No. Contract No. 24-205-10-26 08-0K1224 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 77% Location: Federal Project: 08-SBD-15-R28.6/37.5 B1IM-015-5(167) Progress payment No. 033 Payment period ending: 07-20-24 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,917,907.11 6,060,385.20 2. a. Extra Work 19,440,316.52 1,094,334.93 b. Adustment Comp. 1,174,695.30 16,350.38 3. Materials on Hand 1,968,349.90 -997,913.50 4. Earned Subject to Retention 98,501,268.83 6,173,157.01 5. Mobilization 12,819,642.50 0.00 6. Total Work Completed 109,352,561.43 7. Deductions -893,138.72 -61,938.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 110,427,772.61 6,111,219.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,111,219.01