Dept. of Trans. PROGRESS Serial No. Contract No. 21-203-12-29 08-0K1234 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 67% Location: Federal Project: 08-SBD-15-64.6/75.3 NONE Progress payment No. 010 Payment period ending: 07-20-21 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,851,842.41 560,258.88 2. a. Extra Work 214,580.63 36,329.13 b. Adustment Comp. 889,008.08 0.00 3. Materials on Hand 25,105.00 -10,936.00 4. Earned Subject to Retention 13,980,536.12 585,652.01 5. Mobilization 1,450,000.00 0.00 6. Total Work Completed 15,405,431.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,430,536.12 585,652.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 585,652.01