Dept. of Trans. PROGRESS Serial No. Contract No. 10-057-08-34 08-0K1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 89% 08-RIV-10-56.7/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-22-10 P T M GENERAL ENGINEERING SERVICES INC P O BOX 7745 RIVERSIDE CA 925137745 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 397,949.80 150,667.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 397,949.80 150,667.00 5. Mobilization 19,102.00 0.00 6. Total Work Completed 417,051.80 7. Deductions -15,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 402,051.80 140,667.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,667.00