Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 12-213-14-29 08-0K2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 4% 08-SBD-18-75.3/75.7 Federal Project: ACHS-P018(42) STP-P018(42) Progress payment No. 02 Payment period ending: 07-19-12 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 313,277.50 45,045.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 313,277.50 45,045.00 5. Mobilization 6. Total Work Completed 313,277.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 313,277.50 45,045.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,045.00