Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-079-13-44 08-0K2914 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-10-30.9/33.3 ACIM-010-2(265) Progress payment No. 016 Payment period ending: 08-05-19 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,930,347.35 14,853.74 2. a. Extra Work 204,996.88 6,035.62 b. Adustment Comp. -15,986.19 0.00 3. Materials on Hand 4. Earned Subject to Retention 17,119,358.04 20,889.36 5. Mobilization 1,107,042.00 0.00 6. Total Work Completed 18,226,400.04 7. Deductions -111,354.45 74,300.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,115,045.59 95,189.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,189.36