Dept. of Trans. PROGRESS Serial No. Contract No. 16-300-13-37 08-0K2924 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 36% Location: Federal Project: 08-SBD-10-32.9/R37.4 NHPI-010 2-263(78E) Progress payment No. 008 Payment period ending: 10-20-16 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,274,176.71 0.00 2. a. Extra Work 110,191.86 14,828.38 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 9,384,368.57 14,828.38 5. Mobilization 1,805,000.00 0.00 6. Total Work Completed 11,189,368.57 7. Deductions -30,972.40 2,476.60 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,158,396.17 17,304.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,304.98