Dept. of Trans. PROGRESS Serial No. Contract No. 17-235-10-05 08-0K2924 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 82% Location: Federal Project: 08-SBD-10-32.9/R37.4 NHPI-010 2-263(78E) Progress payment No. 018 Payment period ending: 08-11-17 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,841,721.03 48,001.70 2. a. Extra Work 406,177.74 -57,581.68 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 23,247,898.77 -9,579.98 5. Mobilization 1,900,000.00 0.00 6. Total Work Completed 25,147,898.77 7. Deductions -196,074.40 203,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,951,824.37 193,420.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,420.02