Dept. of Trans. PROGRESS Serial No. Contract No. 19-205-10-40 08-0K2934 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 30% Location: Federal Project: 08-SBD-10-R36.9/R39.1 B1IM-010-2(266) Progress payment No. 006 Payment period ending: 07-20-19 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,564,350.49 1,605,262.78 2. a. Extra Work 257,862.09 41,529.96 b. Adustment Comp. 81,284.65 -18,052.98 3. Materials on Hand 379,404.09 379,404.09 4. Earned Subject to Retention 6,282,901.32 2,008,143.85 5. Mobilization 2,588,750.00 545,000.00 6. Total Work Completed 8,492,247.23 7. Deductions -52,700.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,818,951.32 2,543,143.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,543,143.85