Dept. of Trans. PROGRESS Serial No. Contract No. 19-262-14-23 08-0K2934 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 45% Location: Federal Project: 08-SBD-10-R36.9/R39.1 B1IM-010-2(266) Progress payment No. 008 Payment period ending: 09-20-19 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,181,732.15 2,669,693.34 2. a. Extra Work 308,201.64 37,523.16 b. Adustment Comp. 81,722.93 10,926.36 3. Materials on Hand 452,575.69 10,796.96 4. Earned Subject to Retention 10,024,232.41 2,728,939.82 5. Mobilization 2,588,750.00 0.00 6. Total Work Completed 12,160,406.72 7. Deductions -54,700.00 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,558,282.41 2,736,939.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,736,939.82