Dept. of Trans. PROGRESS Serial No. Contract No. 19-325-09-38 08-0K2934 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 58% Location: Federal Project: 08-SBD-10-R36.9/R39.1 B1IM-010-2(266) Progress payment No. 010 Payment period ending: 11-20-19 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,358,374.56 1,379,533.49 2. a. Extra Work 380,158.47 34,062.55 b. Adustment Comp. 79,775.59 -1,274.00 3. Materials on Hand 440,077.20 -12,498.49 4. Earned Subject to Retention 12,258,385.82 1,399,823.55 5. Mobilization 2,588,750.00 0.00 6. Total Work Completed 14,407,058.62 7. Deductions -49,700.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,797,435.82 1,404,823.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,404,823.55