Dept. of Trans. PROGRESS Serial No. Contract No. 20-203-13-12 08-0K2934 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 94% Location: Federal Project: 08-SBD-10-R36.9/R39.1 B1IM-010-2(266) Progress payment No. 019 Payment period ending: 07-20-20 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,855,716.84 1,383,233.07 2. a. Extra Work 1,259,938.19 8,680.80 b. Adustment Comp. 48,698.65 -95,521.85 3. Materials on Hand 25,478.05 -381,651.95 4. Earned Subject to Retention 24,189,831.73 914,740.07 5. Mobilization 2,725,000.00 0.00 6. Total Work Completed 26,889,353.68 7. Deductions -37,700.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,877,131.73 904,740.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 904,740.07