Dept. of Trans. PROGRESS Serial No. Contract No. 20-266-10-23 08-0K2934 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 08-SBD-10-R36.9/R39.1 B1IM-010-2(266) Progress payment No. 022 Payment period ending: 09-20-20 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,036,575.10 384,135.12 2. a. Extra Work 1,285,014.19 11,326.00 b. Adustment Comp. 44,645.11 -4,053.54 3. Materials on Hand 15,418.59 -5,941.87 4. Earned Subject to Retention 25,381,652.99 385,465.71 5. Mobilization 2,725,000.00 0.00 6. Total Work Completed 28,091,234.40 7. Deductions -38,700.00 26,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,067,952.99 411,465.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 411,465.71