Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-096-13-42 08-0K3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-15-R0.5/R2.6 Federal Project: ACIM-155(154) 54E Progress payment No. 08 Payment period ending: 03-07-12 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,866,795.25 0.00 2.a. Extra Work 60,431.06 2,715.16 b. Adjustment Comp. -5,763.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,921,463.31 2,715.16 5. Mobilization 86,500.00 0.00 6. Total Work Completed 3,007,963.31 7. Deductions -10,399.50 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,997,563.81 2,715.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,715.16