Dept. of Trans. PROGRESS Serial No. Contract No. 09-169-12-47 08-0K7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 49% 08-SBD-215-0.4/4.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-12-09 J MC LOUGHLIN ENGINEERING CO INC 10644 FULTON COURT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 256,408.20 194,704.65 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 256,408.20 194,704.65 5. Mobilization 18,000.00 4,500.00 6. Total Work Completed 274,408.20 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 274,408.20 199,204.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 199,204.65