Dept. of Trans. PROGRESS Serial No. Contract No. 15-358-09-03 08-0K7104 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 68% Location: Federal Project: 08-SBD-15-14.0/R16.4 STPL-6208(16) N-6208(16) ACIM-X071(63) Progress payment No. 038 Payment period ending: 12-17-15 ATKINSON CONTRACTORS LP 18201 VON KARMAN AVE., STE800 IRVINE, CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 186,684,808.18 2,231,325.00 2. a. Extra Work 10,550,719.40 378,489.09 b. Adustment Comp. 5,896,301.17 0.00 3. Materials on Hand 258,710.46 -45,418.45 4. Earned Subject to Retention 203,390,539.21 2,564,395.64 5. Mobilization 6. Total Work Completed 203,131,828.75 7. Deductions -1,127,058.19 19,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 202,263,481.02 2,583,395.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,583,395.64