Dept. of Trans. PROGRESS Serial No. Contract No. 16-175-08-06 08-0K7104 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 77% Location: Federal Project: 08-SBD-15-14.0/R16.4 STPL-6208(16) N-6208(16) ACIM-X071(63) Progress payment No. 044 Payment period ending: 06-16-16 ATKINSON CONTRACTORS LP 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 202,920,389.26 1,230,229.11 2. a. Extra Work 12,624,352.34 1,422,323.00 b. Adustment Comp. 7,133,680.09 1,005,378.92 3. Materials on Hand 124,848.21 -60,745.20 4. Earned Subject to Retention 222,803,269.90 3,597,185.83 5. Mobilization 6. Total Work Completed 222,678,421.69 7. Deductions -1,407,419.97 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 221,395,849.93 3,597,185.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,597,185.83