Dept. of Trans. PROGRESS Serial No. Contract No. 16-238-10-07 08-0K7104 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 81% Location: Federal Project: 08-SBD-15-14.0/R16.4 STPL-6208(16) N-6208(16) ACIM-X071(63) Progress payment No. 046 Payment period ending: 08-18-16 ATKINSON CONTRACTORS LP 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 205,036,962.49 995,050.17 2. a. Extra Work 12,998,538.54 203,248.20 b. Adustment Comp. 7,191,989.17 34,759.00 3. Materials on Hand 31,677.12 -93,171.09 4. Earned Subject to Retention 225,259,167.32 1,139,886.28 5. Mobilization 6. Total Work Completed 225,227,490.20 7. Deductions -2,197,706.81 -394,200.18 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 223,061,460.51 745,686.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 745,686.10