Dept. of Trans. PROGRESS Serial No. Contract No. 16-327-15-51 08-0K7104 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 86% Location: Federal Project: 08-SBD-15-14.0/R16.4 STPL-6208(16) N-6208(16) ACIM-X071(63) Progress payment No. 049 Payment period ending: 11-18-16 ATKINSON CONTRACTORS LP 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 205,845,800.00 112,350.00 2. a. Extra Work 13,487,238.68 121,278.00 b. Adustment Comp. 6,834,299.63 -12,689.54 3. Materials on Hand 4. Earned Subject to Retention 226,167,338.31 220,938.46 5. Mobilization 6. Total Work Completed 226,167,338.31 7. Deductions -2,860,398.30 13,426.68 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 223,306,940.01 234,365.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 234,365.14