Dept. of Trans. PROGRESS Serial No. Contract No. 17-235-10-45 08-0K7104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 95% Location: Federal Project: 08-SBD-15-14.0/R16.4 STPL-6208(16) N-6208(16) ACIM-X071(63) Progress payment No. 058 Payment period ending: 04-14-17 ATKINSON CONTRACTORS LP 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,698,800.00 238,000.00 2. a. Extra Work 15,114,692.16 101,432.64 b. Adustment Comp. 6,834,299.64 0.01 3. Materials on Hand 4. Earned Subject to Retention 228,647,791.80 339,432.65 5. Mobilization 6. Total Work Completed 228,647,791.80 7. Deductions -2,539,620.41 176,892.66 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 226,108,171.39 516,325.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 516,325.31