Dept. of Trans. PROGRESS Serial No. Contract No. 09-085-13-31 08-0K9204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 99% 08-RIV-91-21.5/21.6 Federal Project: NONE Progress payment No. 04 Payment period ending: 03-17-09 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 02410 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,984,230.33 28,003.34 2.a. Extra Work b. Adjustment Comp. -334,958.61 50,749.98 3. Materials on Hand 4. Earned Subject to Retention 1,649,271.72 78,753.32 5. Mobilization 56,000.00 0.00 6. Total Work Completed 1,705,271.72 7. Deductions 8. a.Contract Retentions -82,463.59 -3,937.67 b. Unsatisfactory Prog. -3,937.66 -3,937.66 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,618,870.47 70,877.99 10. Reduction Amt to Escrow 11. Payment to Escrow 82,460.00 12. Net Pymt. this Estimate 70,877.99