Dept. of Trans. PROGRESS Serial No. Contract No. 12-117-13-35 08-0L0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 100% 08-SBD-60-R4.8/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 04-19-12 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD, #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 401,041.55 -2,000.00 2.a. Extra Work b. Adjustment Comp. 64,860.00 64,860.00 3. Materials on Hand 4. Earned Subject to Retention 465,901.55 62,860.00 5. Mobilization 10,000.00 0.00 6. Total Work Completed 475,901.55 7. Deductions -1,785.00 8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 474,116.55 70,860.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,860.00