Dept. of Trans. FINAL Serial No. Contract No. 09-285-09-32 08-0L2904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-38-7.7/15.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-24-09 MANHOLE ADJUSTING CONTRACTORS INC 9500 BEVERLY ROAD PICO RIVERA CA 90660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,525,889.01 0.00 2.a. Extra Work 11,612.37 0.00 b. Adjustment Comp. 60,308.19 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,597,809.57 0.00 5. Mobilization 6. Total Work Completed 1,597,809.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,597,809.57 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00