Dept. of Trans. PROGRESS Serial No. Contract No. 09-239-13-03 08-0L3604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 90% 08-SBD-40-3.0/15.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-09 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE AVE NO 20 ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 901,894.95 901,894.95 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 901,894.95 901,894.95 5. Mobilization 6. Total Work Completed 901,894.95 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -90,189.50 -90,189.50 c. Reduction after 95% Comp. 9. Total pay to Contractor 811,705.45 811,705.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 811,705.45