Dept. of Trans. PROGRESS Serial No. Contract No. 12-116-15-33 08-0M2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 43% 08-SBD-15-107.7/154.6 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-19-12 TRUESDELL CORPORATION OF CALIFORNIA INC 1310 W 23RD STREET TEMPE AZ 85282 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,839.77 0.00 2.a. Extra Work 29,000.00 7,000.00 b. Adjustment Comp. -47,421.84 0.00 3. Materials on Hand 710,514.20 90,219.00 4. Earned Subject to Retention 898,932.13 97,219.00 5. Mobilization 188,606.35 0.00 6. Total Work Completed 377,024.28 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,087,538.48 97,219.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,219.00