Dept. of Trans. PROGRESS Serial No. Contract No. 10-266-12-51 08-0M5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 71% 08-SBD-5708 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-16-10 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 250,051.19 124,385.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 250,051.19 124,385.50 5. Mobilization 6. Total Work Completed 250,051.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 250,051.19 124,385.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 124,385.50