Dept. of Trans. PROGRESS Serial No. Contract No. 13-114-14-11 08-0M8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 08-RIV-74-27.4/27.7 Federal Project: ACHS-P074(56) STPG Progress payment No. 06 Payment period ending: 04-18-13 FLATIRON ELECTRIC GROUP INC 7911-A PINE AVENUE CHINO CA 91708 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 290,613.60 57,735.10 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 290,613.60 57,735.10 5. Mobilization 30,000.00 0.00 6. Total Work Completed 320,613.60 7. Deductions -9,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 13,027.90 c. Reduction after 95% Comp. 9. Total pay to Contractor 311,613.60 70,763.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,763.00