Dept. of Trans. PROGRESS Serial No. Contract No. 13-057-16-08 08-0M94U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 0% 0% 08-RIV-215-43.2/45.3 Federal Project: 08-SBD-215-0.0/5.1 OTHR 08-RIV-91-21.5/21.7 STPL-6208(18) PLN-6208(18) Progress payment No. 01 Payment period ending: 02-20-13 AMES CONSTRUCTION INC 391N MAIN ST STE 111 CORONA CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,471.34 59,471.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 59,471.34 59,471.34 5. Mobilization 6. Total Work Completed 59,471.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,471.34 59,471.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,471.34