Dept. of Trans. PROGRESS Serial No. Contract No. 14-024-16-37 08-0M94U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 42% 08-RIV-215-43.2/45.3 Federal Project: 08-SBD-215-0.0/5.1 OTHR 08-RIV-91-21.5/21.7 STPL-6208(18) PLN-6208(18) Progress payment No. 12 Payment period ending: 01-17-14 AMES CONSTRUCTION INC 2000 AMES DRIVE BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,471,981.74 2,489,558.60 2.a. Extra Work 900,335.27 90,718.91 b. Adjustment Comp. 153,052.48 52,500.00 3. Materials on Hand 13,061,357.69 2,579,729.71 4. Earned Subject to Retention 42,586,727.18 5,212,507.22 5. Mobilization 12,350,000.00 0.00 6. Total Work Completed 41,875,369.49 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 54,936,727.18 5,212,507.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,212,507.22