Dept. of Trans. FINAL Serial No. Contract No. 17-241-10-47 08-0M94U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-215-43.2/45.3 OTHR 08-SBD-215-0.0/5.1 STPL-6208(18) 08-RIV-91-21.5/21.7 PLN-6208(18) Progress payment No. 043 Payment period ending: 08-21-15 AMES CONSTRUCTION INC 2000 AMES DR BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 108,369,950.27 0.00 2. a. Extra Work 6,161,425.33 0.00 b. Adustment Comp. 8,666,876.13 0.00 3. Materials on Hand 4. Earned Subject to Retention 123,198,251.73 0.00 5. Mobilization 13,000,000.00 0.00 6. Total Work Completed 136,198,251.73 7. Deductions -5,000.00 48,240.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 136,193,251.73 48,240.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,240.00