Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-08-46 08-0N0704 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 93% Location: Federal Project: 08-RIV-91-0.0 NONE Progress payment No. 005 Payment period ending: 06-20-25 JPUS BUILDERS CORP 8916 JASMINE DR BUENA PARK CA 90621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,600.00 0.00 2. a. Extra Work 1,790,235.93 139,136.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,811,835.93 139,136.07 5. Mobilization 6. Total Work Completed 1,811,835.93 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,791,835.93 139,136.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,136.07