Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-08-24 08-0N0804 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 43% Location: Federal Project: 08-SBD-15-0.0 NONE Progress payment No. 002 Payment period ending: 12-20-24 JPUS BUILDERS CORP 3010 W ORANGE AVE #102 ANAHEIM CA 92804 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 544,715.86 360,249.76 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 544,715.86 360,249.76 5. Mobilization 6. Total Work Completed 544,715.86 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 539,715.86 355,249.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 355,249.76