Dept. of Trans. PROGRESS Serial No. Contract No. 10-299-16-16 08-0N3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 51% 08-RIV-60-13.3/30.4 Federal Project: ACNH-P060(137) Progress payment No. 02 Payment period ending: 10-20-10 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,449,156.79 1,853,494.42 2.a. Extra Work b. Adjustment Comp. -31,193.39 -31,193.39 3. Materials on Hand 4. Earned Subject to Retention 2,417,963.40 1,822,301.03 5. Mobilization 6. Total Work Completed 2,417,963.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,417,963.40 1,822,301.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,822,301.03