Dept. of Trans. PROGRESS Serial No. Contract No. 10-328-09-20 08-0N3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 51% 08-RIV-60-13.3/30.4 Federal Project: ACNH-P060(137) Progress payment No. 03 Payment period ending: 11-19-10 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,499,640.01 50,483.22 2.a. Extra Work b. Adjustment Comp. -31,193.39 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,468,446.62 50,483.22 5. Mobilization 6. Total Work Completed 2,468,446.62 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,468,446.62 50,483.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,483.22