Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-10-04 08-0N6704 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 69% Location: Federal Project: 08-RIV-74-28.1/37.4 HSNH-P074(67) STPH Progress payment No. 015 Payment period ending: 11-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,928,206.87 928,251.55 2. a. Extra Work 1,221,778.36 0.00 b. Adustment Comp. 658,080.00 658,080.00 3. Materials on Hand 70,982.95 -412,858.05 4. Earned Subject to Retention 10,879,048.18 1,173,473.50 5. Mobilization 1,123,559.00 0.00 6. Total Work Completed 11,931,624.23 7. Deductions -4,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,998,607.18 1,173,473.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,173,473.50