Dept. of Trans. PROGRESS Serial No. Contract No. 11-333-13-36 08-0N8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 39% 08-RIV-10-38.8/42.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-18-11 DREAMBUILDER 1361 EAST GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 188,677.40 98,589.50 2.a. Extra Work 13,869.16 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 202,546.56 98,589.50 5. Mobilization 68,342.34 14,387.86 6. Total Work Completed 270,888.90 7. Deductions -6,976.54 -4,626.64 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 263,912.36 108,350.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,350.72