Dept. of Trans. PROGRESS Serial No. Contract No. 15-147-14-30 08-0P2804 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 39% Location: Federal Project: 08-RIV-60-R1.5 HSNH-P060(145) Progress payment No. 002 Payment period ending: 05-20-15 POWELL CONSTRUCTORS, INC. 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 583,793.93 358,046.78 2. a. Extra Work 47,495.47 47,495.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 631,289.40 405,542.25 5. Mobilization 100,000.00 5,000.00 6. Total Work Completed 731,289.40 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 725,289.40 404,542.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 404,542.25