Dept. of Trans. PROGRESS Serial No. Contract No. 19-325-09-36 08-0P3904 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 49% Location: Federal Project: 08-SBD-18-101.5/115.9 HSNH-P018(62) Progress payment No. 008 Payment period ending: 11-20-19 C A RASMUSSEN INC 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,447,720.35 1,285,481.38 2. a. Extra Work 115,966.54 3,540.38 b. Adustment Comp. 3,910.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,567,596.89 1,289,021.76 5. Mobilization 1,429,000.00 0.00 6. Total Work Completed 10,996,596.89 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,976,596.89 1,279,021.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,279,021.76