Dept. of Trans. PROGRESS Serial No. Contract No. 13-057-16-12 08-0P6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 98% 08-RIV-15-3.2/52.3 Federal Project: ACST-P000(C33) Progress payment No. 16 Payment period ending: 02-20-13 CALIFORNIA PROFESSIONAL ENGINEERING, INC. 929 OTTERBEIN AVENUE UNIT E LA PUENTE CA 91748 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,593,500.00 139,470.00 2.a. Extra Work 67,139.10 42,072.74 b. Adjustment Comp. -77,461.00 -77,461.00 3. Materials on Hand 4. Earned Subject to Retention 1,583,178.10 104,081.74 5. Mobilization 24,000.00 0.00 6. Total Work Completed 1,607,178.10 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,602,178.10 104,081.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,081.74