Dept. of Trans. FINAL Serial No. Contract No. 13-080-09-00 08-0P8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-10-0.0/9.2 Federal Project: NONE Progress payment No. 08 Payment period ending: 12-21-12 FBD VANGUARD CONSTRUCTION INC 651 ENTERPRISE CT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,313,133.79 0.00 2.a. Extra Work 442,297.85 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,755,431.64 0.00 5. Mobilization 215,000.00 0.00 6. Total Work Completed 2,970,431.64 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,970,431.64 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00