Dept. of Trans. PROGRESS Serial No. Contract No. 16-083-12-22 08-0Q2004 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 38% Location: Federal Project: 08-RIV-10-1.0 NONE Progress payment No. 003 Payment period ending: 03-17-16 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 339,758.43 165,414.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 339,758.43 165,414.00 5. Mobilization 66,500.00 0.00 6. Total Work Completed 406,258.43 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 396,258.43 155,414.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,414.00