Dept. of Trans. PROGRESS Serial No. Contract No. 17-331-16-10 08-0Q3004 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 34% Location: Federal Project: 08-SBD-138-17.1/19.2 HSNH-P P138-055(E) Progress payment No. 017 Payment period ending: 11-17-17 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA RD RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,446,839.37 959,772.31 2. a. Extra Work 762,622.70 263,857.77 b. Adustment Comp. 7,404.49 0.00 3. Materials on Hand 48,233.32 -39,449.45 4. Earned Subject to Retention 14,265,099.88 1,184,180.63 5. Mobilization 2,100,000.00 0.00 6. Total Work Completed 16,316,866.56 7. Deductions -20,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,345,099.88 1,189,180.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,189,180.63