Dept. of Trans. PROGRESS Serial No. Contract No. 18-058-12-58 08-0Q3004 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 42% Location: Federal Project: 08-SBD-138-17.1/19.2 HSNH-P P138-055(E) Progress payment No. 020 Payment period ending: 02-16-18 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA RD RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,995,393.24 688,841.66 2. a. Extra Work 851,839.33 89,216.63 b. Adustment Comp. 61,578.50 54,174.01 3. Materials on Hand 71,900.37 -47,264.58 4. Earned Subject to Retention 16,980,711.44 784,967.72 5. Mobilization 2,100,000.00 0.00 6. Total Work Completed 19,008,811.07 7. Deductions -200,185.51 -200,185.51 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,880,525.93 584,782.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 584,782.21