Dept. of Trans. PROGRESS Serial No. Contract No. 16-008-09-01 08-0Q4704 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 86% Location: Federal Project: 08-SBD-15-29.6/70.1 NHPI-015-1(234) Progress payment No. 003 Payment period ending: 12-18-15 SULLY-MILLER CONTRACTING COMPANY 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,990,538.96 406,164.23 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,990,538.96 406,164.23 5. Mobilization 156,670.00 0.00 6. Total Work Completed 3,147,208.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -40,616.42 -40,616.42 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,106,592.54 365,547.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 365,547.81