Dept. of Trans. PROGRESS Serial No. Contract No. 11-147-12-58 08-0Q5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 82% 08-SBD-330-36.2/44.1 Federal Project: 08-SBD-330-0.0 ER Progress payment No. 02 Payment period ending: 05-20-11 SEMA CONSTRUCTION INC. 6 ORCHARD SUITE 150 LAKE FOREST, CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 485,792.10 308,880.10 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 485,792.10 308,880.10 5. Mobilization 6. Total Work Completed 485,792.10 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -30,888.01 -30,888.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 454,904.09 277,992.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,992.09